The NJ Department of Community Affairs has issued the following guidance for use in addressing electrical systems in the aftermath of Hurricane Sandy:
Panel underwater o Pull the meter o Clean and dry all breakers and bus bar o Reinstall breakers necessary for temporary occupancy and restoration o Within 90 days, all breakers and bus bar must be replaced. In lieu of replacement, the bus bar may be certified by a licensed electrical contractor
Wiring underwater o If undamaged, no replacement is necessary
Other equipment and outlets (receptacles, lighting, switches, alarms, etc.) underwater o Within 90 days, all other equipment and outlets must be replaced |